Agenda

AGENDA

The City of Alma Municipal Building Committee of the City of Alma will hold a meeting on Wednesday, June 3, 2026 at 9:00 a.m. at the City Hall – 314 Main St. N., Alma, WI to discuss and act upon the following:

  1. Roll Call
  2. Updates on Demolition
  3. Projected Timelines of Reconstruction
  4. Review, Discuss and Approve Construction Bulletins for Phase 1.
  5. Review, Discuss, Modify and Approve Construction Plans for Phase 2.
  6. Move to Submit Phase 2 Plans to the State for Approval
  7. Any other items properly brought before the committee

Larry Grisen
Chairperson

NOTICE IS HEREBY GIVEN, that a majority of the Common Council may be present in order to gather information on a subject which may require a vote at a later date.

Minutes

June 3, 2026 City of Alma Municipal Building Committee 9:00 a.m.
314 N. Main St., Alma, WI

Chairperson Larry Grisen called the meeting to order with the following members present: Richard Champeny, David Earney, Clerk-Treasurer Sharaya Reed, and Deputy Clerk Michaela Handke.

Also present: Breanna Guntner and Bill Boettcher from the architect firm of Lien and Peterson, Joe Wick and Justin Sass.

Boettcher provided updates on the demolition. The demolition is pretty much complete. The new roof is on.

The projected timeline of the reconstruction is still on track to be completed by early September. The new windows will be coming at the end of June.

Construction Bulletins 1-27 for Phase 1 were reviewed, discussed, and approved as follows:

Alma City Hall Remodel Construction Bulletins
CB # CO # Title Description Pricing Action
1 Window Head and Sill Repair of the window heads and sills. At the window heads, remove all finishes to the original plaster finish. At the exterior head, remove the cover metal on the exterior, repair the damaged wood blocking, and prepare for installation of new windows. Replace cover metal as required. For the sill, remove damaged wood material and replace with new. Install new base flashing as required to make installation water tight. $7,889.90 Motion by Earney seconded by Champeny to approve. All members voting yes by roll call vote.
2 Floor Patching and Feathering Patch the holes in the floor where the interior walls were removed. In addition, feather in the floor between the two sides to provide a smooth transition between the two floor areas. $7,931.07 Motion by Earney seconded by Grisen to approve. All members voting yes by roll call vote.
3 Bulkhead at Clerk Counter Construct a new bulkhead above the clerk counter area. The bulkhead is to be constructed with metal studs with sheetrock per the attached detail. Height of bulkhead to match existing ceiling height. $2,076.92 Motion by Earney seconded by Champeny to approve. All members voting yes.
4 Rebuild Breakroom Wall Remove the west breakroom wall and replace with a new stud wall. The existing wall is in poor shape and this will allow for a better finished product. $2,119.32 Motion by Earney seconded by Grisen to approve. All members voting yes.
5 Security Camera Conduit and Wiring Installation Install conduit and wiring for eleven security cameras as shown on the attached two sheets. Wiring to be CAT6. Terminations to be by camera installer. $7,419.41 Motion by Champeny seconded by Earney to approve. All members voting yes by roll call vote.
6 Telecommunications Design and Installation Design and install the telecommunications system. This system shall include cabling, terminations, testing, labeling and adhering to current standards. This work will need to be coordinated with City of Alma staff and their chosen IT vendors. $25,390.10 Motion by Earney seconded by Champeny to approve. All members voting yes by roll call vote.
7 Interior Wall Support Brace the existing walls. Secure the wall with Unistrut on each side of the wall to the bar joists above. For the furred wall in the lobby, secure the wall to the adjacent wall using Simpson A21 attached to the top plate with nails, and attached to the backing wall with nails or Tapcon as required. $1,503.63 Motion by Earney seconded by Handke to approve. All members voting yes.
8 Walls Below Windows Repair the walls below the windows. Remove plaster/gypsum board and sills below the windows. Replace with a mew layer of 1/2” thermax insulation and gypsum board. $4,720.05 Motion by Champeny seconded by Earney to approve. All members voting yes.
9 Mayor’s Office Walls Remove all of the existing wood paneling inside of the Mayor’s Office. Install new drywall as required. $2,342.70 Motion by Champeny seconded by Earney to approve. All members voting yes.
10 Base in Vault Install 4” vinyl base to match office rooms. $624.98 Motion by Earney seconded by Reed to approve including figure from #21 ($448.42) totaling $1,073.40. All members voting yes.
11 Window Sills Remove existing window sills and install new wood window sills. Sill material to be 1x material with apron board to stiffen the front edge. To be revisited when price becomes available.
12 Fluted Metal Panel in Room 111 Remove fluted metal panel in room 111. 3/4″ plywood to be installed on existing clay tile for mounting electrical equipment to on all three walls. To be revisited when price becomes available.
13 Closet 117B Removal of the existing accordion door. Replace with new wood bifold door of normal height. Install wood stud wall above. $2,672.84 Motion by Earney seconded by Reed to approve. All members voting yes.
14 Patching of Duct Openings Patch the existing ductwork openings. Infill with wood stud and drywall. $1,047.39 Motion by Earney seconded by Grisen to approve. All members voting yes.
15 Steel Beam in Lobby Floor Remove existing steel beam in lobby floor. Cut out beams and patch with new concrete floor. $95.53 Motion by Earney seconded by Champeny to approve. All members voting yes.
16 Plumbing Insulation Re-insulate remaining plumbing piping left over from asbestos abatement. To be revisited when price becomes available.
17 CREDIT: Rough-Ins Credit for concrete removal and 3” waste line connection into the garage for installation of future plumbing rough-ins. Work is no longer part of this project scope. This piping will be installed in the future phase 2 and tie into piping in garage. CREDIT
18 Slip Lining Sewer Pipes Install new liner in existing sewer pipes in building. Line to extend from plan North bathroom to mechanical room and from break room to exterior of building. $29,864.94 Already approved at Council.
19 Steel Decking Repair Install new type A roof deck over top of existing damaged roof deck. $15,085.03 Motion by Champeny seconded by Earney to approve. All members voting yes by roll call vote.
20 Downspout At Front Entry Install new downspout at West side of entry roof. Downspout to extend into yard area. $538.91 Motion by Earney seconded by Champney to approve. All members voting yes.
21 Install 6″ Base Replace 4” base called for in plan with 6” vinyl base to hide damage at base of wall in the vault, police, fire, and foreman’s office. $448.42 Figured into motion from #10.
22 Plumbing Exploration Perform underground examination of the existing plumbing/piping with a video camera. To be revisited when price becomes available.
23 Air Conditioner Sleeve Patch hole through wall. Install new brick to match on the exterior. Install masonry infill in clay tile wall. $1,217.07 Motion by Earney seconded by Reed to approve. All members voting yes.
24 Women’s Toilet Room Floor Drain Install a floor drain in Women’s Room 120 per plan approval drawings send via separate email. To be revisited when price becomes available.
25 Insulate Existing Roof Drain Pipes in Office Area Insulate existing roof drain piping in office portion of building. To be revisited when price becomes available.
26 Furnish and Install Break Room Range Hood Furnish and install range hood and associated roof hood above range in Break Room. To be revisited when price becomes available.
Total $111,771.14
-$29,864.94 CREDIT
= $81,906.20
Motion by Earney seconded by Champeny to approve & forward to Council for approval. All members voting yes by roll call vote.

Brief discussion of pressure washing the front of the building.

Jurowski pay app #3 was reviewed.

Motion by Earney seconded by Grisen to approve $204,839.71 for Jurowski pay app #3 and present to Council. All members voting yes by roll call vote.

Construction plans for Phase 2 were reviewed and discussed. Discussion over moving 6″ water line/hydrant across the street.

Motion by Earney seconded by Champeny to approve the Phase 2 plans. All members voting yes by roll call vote.

Motion by Champeny seconded by Earney to approve submitting Phase 2 plans to the State. All members voting yes.

Other items discussed were:

Handke is working on letters to out in the mail to businesses supporting the project with a donation.

There was discussion over the top shed garage door being replaced.

Motion by Champeny seconded by Earney to Adjourn. All members voting yes.